Cenergy Holdings says its Hellenic Cables business has signed the turnkey contract for the Corinth–Kos electricity interconnection with Greek grid operator IPTO. The contract, signed through wholly owned subsidiary Fulgor, is worth about €1.5 billion. Work is due to begin in the fourth quarter of 2026 and finish in 2030.

The 320 kV high-voltage direct-current link will have 1 GW of capacity and connect the Dodecanese islands with mainland Greece. It includes about 1,260 km of submarine cable and 30 km of underground cable. Hellenic Cables is responsible for engineering, procurement, construction and installation from one converter station to the other, and will manufacture the main HVDC cables in Corinth and Thiva.

The supply chain also reaches another ETE company. Nexans has a subcontract with Hellenic Cables and Asso.subsea to deliver a 420 km mass-impregnated 110 kV cable system. Nexans says production-line work and a seabed survey have started. The programme is expected to use its MI cable lines from the end of 2026 through 2027 and into mid-2028. It did not disclose the subcontract value.

The signing matters because Cenergy’s August announcement described an award whose contract still depended on stated conditions and approvals. That uncertainty is now reduced, but €1.5 billion is a multi-year project value, not immediate revenue. Delivery timing, project costs and margins remain undisclosed. The next evidence will be execution against the 2030 schedule and how the order flows through Cenergy’s backlog, revenue and cash generation.